Week #22 Visible Progress
Week #22 brought many positive comments from those who drove by the library.
“The Library is looking good!“
“What a big difference!“
New siding on the addition & on the existing library was the biggest improvement noticed.
Add to that some new steps & ramps & a condenser pad.
And, top it off with some volunteer labor to help clear out the fallen leaves & dried up marigolds that lined our front walk.
Inside the library, doors & windows are ready to be stained. Trim is ready for installation.
PROGRESS is pressing on!
Check back next week for more updates… 🙂